Sunday, 18 November 2012

Update - Mid-November

This is what's been done in the last few weeks:
  • Colorbond roof and guttering - almost complete
  • Rendering complete
  • Plumbing and gas rough-in complete.
  • Electrical rough-in complete.
  • Ducted air conditioning rough-in complete.
  • Gyprock ceilings done
  • Brick cleaning - about half way
  • Windows - almost done
  • Waterproofing of wet areas - started
  • Timber flooring - started 
  • Internal Painting - started